References

Liege Airport

Liege Airport Liege Airport Liege Airport

Project display

Installation of a 637 kWe cogeneration unit and a heat network supplying eight substations within Liège Airport.

Project specificity

  • Installation of a cogeneration, a heat network and a planned extension towards a trigeneration.
  • Adaptation of energy substations for current heating needs.
  • Configuration of the boiler room of the airport terminal into back-up for the new network.
Télécharger la brochure

Similar projects

ANNUAL GAINS

ANNUAL GAINS

CO2 savings

384 T/year

Electricity production

3900 MWh

Payback time

3,5 years

INSTALLATION

INSTALLATION

Brand

GE Jenbacher

Type

JMS 312 D05

Gas consumption

1550 kW

Hot water power high T°

752 kW

Hot water power low T°

45 kW

Electrical power

637 kW

Nominal total return

92,5 %

Heat network

1,8 km for 8 substations

PLANNING

PLANNING

Project start

September 2014

Temporary reception

July 2015