References

Municipal administration of Attert

Municipal administration of Attert Municipal administration of Attert Municipal administration of Attert

Project display

The municipal administration of Attert called on CORETEC Energy to reduce its heat consumption. For this purpose, a 220 kth boiler, a centralised regulation and a 170 m heat network with possible future expansion were installed, generating an annual saving of € 22,450.

Project specificity

  • Call for tender
Télécharger la brochure

Similar projects

ANNUAL GAINS

ANNUAL GAINS

CO2 savings:

92 T/year

SO2 savings:

117 KG /year

Payback time:

6,4 years

INSTALLATION

INSTALLATION

Brand:

Köb

Type:

Pyrot 220

Fuel:

Wood shavings

Consumption:

112T/year

Thermal power :

220 kW

Nominal total return:

92 %

Heat network:

170m

PLANNING

PLANNING

Project start:

May 2011

Temporary reception:

September 2011