Project display

Installation of a gas turbine and a steam turbine within the company Idempepers.

Project specificity

  • Second-hand installation transferred from a site in Dartford (UK)
Télécharger la brochure

ANNUAL GAINS

ANNUAL GAINS

Electricity production

70 GWh

Primary energy savings

73,5 GWh

CO2 savings

14.700T/year

Annual profit

3,9M€

Payback time

3,3 ans

INSTALLATION

INSTALLATION

Brand

SIEMENS / FOSTER WHEELER

Type

Turbine gaz / vapeur

Electrical power

6,2MW – gas turbine

Electrical power

3,4MW – steam turbine

Steam production

50 T/h

Nominal total return

90%

PLANNING

PLANNING

Project start

June 2010

Temporary reception

July 2012