Joskin Polska entrusted CORETEC Energy with reducing its energy costs associated with its galvanising activity. Two cogeneration units were installed, generating a total annual saving of more than € 160,000 for the company.

Project specificity

  • 1st international project
Télécharger la brochure

Similar projects

ANNUAL GAINS

ANNUAL GAINS

Electricity production

2.508 MWh

CO2 savings

370 T/year

Annual profit

162.000 €

Payback time

2,4 years

INSTALLATION

INSTALLATION

Brand

TEDOM

Installed unit type

2x Cento T160

Gas consumption

870 kW

Electrical power

320 kW

Thermal power

450 kW

Running hours

8000h/year

Nominal total return

89 %

PLANNING

PLANNING

Project start

June 2011

Commissioning

June 2012